Delta Water Supply Project 
Contractors & Subcontractors
INTAKE AND PUMP STATION FACILITY
On August 25, 2009, the Stockton City council approved a contract with Preston Pipelines for $16,156,000 for construction of the Delta Water Supply Project (DWSP) Intake and Pump Station Facility. Listed below are Preston's proposed subcontractors:
- Devcon Construction
- Bockman & Woody Electric
- Big B Construction
- Ghilotti Brothers/Cooper Crane & Rigging
- AM Stephens Construction
- Wallace Kuhl & Associates
- Neil O. Anderson & Associates
- FD Thomas
On August 25, 2009, the Stockton City Council approved a contract with Carollo Engineers for $1,599,260 for construction management services associated with the DWSP Intake and Pump Station Facility.
WATER TREATMENT PLANT AND PIPELINES
On August 25, 2009, the Stockton City Council approved a contract with CDM Constructors, Inc. for $166,457,371 for construction of the DWSP pipelines and water treatment plant. Listed below are CDM's major, proposed subcontractors:
- Sundt Construction
- Vadnais Corporation
- DYK Incorporated
- Fluid IQs
- John Jackson Masonry
- Monterey Mechanical Co.
- Preston Pipelines
- Kinetics Mechanical Service Inc.
- San Joaquin Electric Inc.
- Teichert Construction
- Construction Testing Services